October 2026 Progress Update
Construction Progress Milestones
Building with transparency
Construction Progress
Overall project progress
18%
According to our internal inspection conducted on 31-10-2026, the overall project's progress is 18%
Project Timeline 2026
At Misa Property Developers, we are committed to keeping our investors informed at every stage of construction. This timeline shares monthly progress updates, completed works, key milestones and site photographs for Misa Luxe 1. Our focus remains on quality, transparency and long-term value as the project moves forward.
2026 October
Construction Progress Milestones
1. Capping beam construction is progressing, with 30m completed out of the total 132m.
2. Provisions for future electrical, water supply, drainage and fire protection services have been incorporated into the roadside capping beam.
3. A temporary stormwater drainage connection to the CMC system has been established. Silt trap construction is complete, with dewatering system testing underway.
4. King posts and walers have been delivered to the site. Basement excavation is scheduled to commence on 3 November, undertaken by specialist contractor San Pilling (Pvt) Ltd.
5. Arrangements for diaphragm wall inclinometer monitoring are underway to enable early detection of structural movement during excavation.
6. Rear boundary wall construction is 85% complete, with western boundary works scheduled to commence on 9 November.